East Bay Office Relocation Timeline: A 90-Day Plan

Here’s a call our crews take more often than you’d think. The new suite is ready, the team starts there Monday, and the property manager has just said the freight elevator is booked out two weeks and won’t release the dock without a certificate of insurance. None of that is unusual, only late. This office relocation timeline breaks a 90-day East Bay move into six working windows, built around the things that actually set the pace: building paperwork, elevator calendars, circuit install dates, and twelve years of accumulated electronics that can’t go in a dumpster.

ShipShape Moving crew packing and relocating office furniture and equipment during a commercial move

Jump to a window:

Why an Office Relocation Timeline Starts 90 Days Out

Ninety days isn’t padding. It’s the longest lead time on the critical path, and in most East Bay buildings that’s the internet circuit. A business fiber install into an existing suite gets quoted in weeks, not days, and if the building needs a new entrance conduit it runs longer. Nothing else on this list matters if your team arrives Monday to a working desk and a dead connection.

Behind the circuit sit three more schedules you don’t control: the landlord’s insurance approval, the building’s freight elevator calendar, and the lead time on furniture you’re buying rather than moving. Ninety days lets those overlap instead of stack.

Here’s the whole plan at a glance:

Window What happens What’s driving the deadline
Days 90–75 Read the exit clause, inventory the office, book the survey Restoration obligations and circuit lead time
Days 75–60 Name a move lead, build the checklist, order internet and furniture Telecom install dates and furniture delivery
Days 60–45 Reserve freight elevators and docks at both buildings Elevator calendars book weeks out
Days 45–30 Confirm packing scope, plan the IT cutover, schedule e-waste Recycler pickups and IT provider availability
Days 30–14 File parking permits, get the COI approved City posting rules and landlord approval time
Days 14–0 Confirm everything in writing, label, move Nothing new starts here

Days 90–75: Scope and Budget for an East Bay Office Move

Start with the lease you’re leaving, not the one you’re signing. Find the restoration language: who patches walls, who pulls the cabling out of the ceiling, who takes the signage down, and what condition the suite has to be in on the day you hand back keys. Restoration is the most common surprise cost in an East Bay office move, and it’s a lot cheaper to schedule in week one than to discover in week twelve.

Then count what you’re moving. Walk the floor with a phone camera and log workstations, private offices, conference rooms, the server closet, the kitchen, and storage, flagging anything that needs disassembly, anything over 300 pounds, and anything with a glass top. A vague inventory gets you a vague estimate.

Book your survey in this window and get the estimate in writing, with crew size, truck count, and hourly or flat structure spelled out.

And if the new suite won’t be ready when the old lease ends — a gap of a week or two is common when a build-out slips — sort out interim storage now, not in week two of the move.

Days 75–60: Build the Office Move Checklist

This is where the move stops being one person’s problem. Name a move lead with authority to decide things, and a point person in each department. The office move checklist that actually works isn’t one list — it’s a master schedule plus a one-page sheet each department fills in for itself.

The master schedule should carry, at minimum:

  • Internet and phone — order placed, install date confirmed, old service disconnected only after the new one is live
  • Furniture — what moves, what’s bought, what’s disposed of, with delivery dates
  • Floor plan — a numbered seating map for the new suite, matched to the labels going on boxes and furniture
  • Address change — bank, insurance, state registration, licensing, payroll, vendors, business listings, website, email signatures, printed collateral
  • Keys, fobs, and alarm codes — who issues them, when, and who collects the old ones

The numbered floor plan is the highest-leverage item on the list. Our crews don’t guess where things go; they read labels. A suite where every room and desk has a number, and every box carries that number, unloads far faster than one where the boxes say “Marketing.”

Days 60–45: Freight Elevators and Building Rules When Moving an Office in Oakland

Commercial buildings run moves on their own terms, and those terms are usually written down. Ask each property manager for the move-in and move-out policy before you book anything. What comes back is usually some mix of a reserved freight elevator window, protective padding and floor runners, a specific loading dock, and a hard cutoff for building access.

Freight elevator slots are the constraint that most often forces a date change. In a multi-tenant tower around Uptown or Jack London Square the calendar books weeks out, and slots are often restricted to evenings and weekends. Reserve both ends in this window — the building you’re leaving and the one you’re entering — and get it in writing.

The same goes across the inner East Bay: if your new suite is in Emeryville, expect a second policy document and a second reservation. Two buildings means two sets of rules, two dock schedules, and two insurance approvals.

Ask early whether your move needs to happen outside business hours to fit the building’s window.

Days 45–30: Packing, IT Cutover, and E-Waste in an East Bay Office Move

Packing an office differs from packing a home in density and liability: files, monitors, and the contents of a supply closet are heavy, fragile, and confidential in roughly equal measure. Decide here whether staff pack their own desks or you hand the job to professional packing. The hybrid is most common — employees clear their own drawers into labeled crates, and the crew takes conference rooms, the kitchen, storage, and anything breakable.

The IT cutover needs its own owner and sequence. Photograph the back of the rack before anything is unplugged, label both ends of every cable, and back everything up — then verify the backup and keep it off the truck. Agree in advance who disconnects and who reconnects. The gap between “the movers don’t touch servers” and “we assumed the movers were handling it” is where a Monday outage lives.

Then deal with the electronics you’re not taking. Old monitors, desktops, UPS units, and printers can’t go in a dumpster in California — they’re covered e-waste and have to go to a certified recycler. Purge drives before anything leaves the building and keep the certificate of destruction. Shred paper archives past their retention window now, rather than paying to move and store them.

Days 30–14: Permits, Parking, and the Office Move Certificate of Insurance

Two pieces of paperwork decide whether move day starts on time.

The first is street access. If the truck can’t legally sit at the curb outside either building, the crew carries everything further and a five-hour job quietly becomes seven. Most East Bay cities issue temporary no-parking or obstruction permits for exactly this, and they need lead time and posted notice. Our guide to obstruction and no-parking permits covers how far ahead to file. Requirements differ by city, so a suite in Alameda is its own application, not a copy of the one you already filed.

Moving truck parked at the curb with its ramp down outside a multi-unit building

The second is the office move certificate of insurance. Nearly every commercial landlord wants a COI from your mover before it will release the freight elevator or the dock, naming the building owner and property manager as additional insureds at the limits the lease specifies. Send the property manager’s exact requirements over as soon as you have them, and treat the returned certificate as a gate on the schedule: no approved COI, no move.

Also in this window: confirm the elevator reservations you booked, line up furniture assembly labor, and send staff the seating map with their own desk number on it.

Days 14–0: Move Weekend and the Last of the Office Move Checklist

The last fortnight is confirmation, not planning. Re-confirm the crew, the trucks, the elevator windows, the dock times, the permits, and the COI approval — in writing, with both property managers copied. Check that the circuit at the new suite is live and tested, not merely installed.

In the final week, have everyone clear and label their own desk, take laptops home rather than sending them on the truck, and empty the kitchen. Post the numbered floor plan at the new suite’s entrance and in the elevator lobby so the crew can read it without asking.

Move day runs on labels and a walkthrough. Keep the move lead on site at both ends. Sweep the old suite — every drawer, every closet, above every cabinet — before the last truck pulls away. At the new suite, check the count against the inventory, note any damage while the crew is still there, and get the network up first.

Then plan for the first Monday to be imperfect. Hold the old suite’s keys until the restoration walkthrough is signed off, and give yourself a punch-list week.

Office Relocation Timeline FAQs

How long does an office move take?

Arrow Down

Plan 90 days from decision to move day for a typical small or mid-size office. The pace is set by internet install lead times and building elevator calendars, not by the lifting. The physical move is usually one day, or a Friday evening through Sunday for anything larger.

What is a certificate of insurance, and who needs one?

Arrow Down

A COI is proof of your moving company’s liability and workers’ compensation coverage, issued to your landlord and naming the building owner and property manager as additional insureds. Most commercial buildings will not permit a move without one on file, and the required limits are set by your lease.

Should we move over a weekend?

Arrow Down

Usually yes. Weekend and after-hours moves fit the freight elevator windows most multi-tenant buildings enforce, and they cost one day of downtime instead of two. Book earlier, though, because weekend slots go first.

What happens to furniture and electronics we are not taking?

Arrow Down

Usable furniture can often be sold or donated if you start early enough to schedule a pickup. Electronics are covered e-waste in California and must go to a certified recycler. Wipe or destroy any drive that held company or customer data first, and keep the certificate.

ShipShape crew and moving truck parked outside a large commercial building before an office move

Let Us Handle the Building Side

Elevator windows, COIs, dock times, e-waste pickups: it’s a stack of logistics landing on a week when the team still has to get work done. ShipShape handles office relocations across the East Bay, from the survey and the COI through elevator scheduling, packing, the move itself, and e-waste haul-away. We work with businesses relocating within Oakland as well as companies arriving from elsewhere in the Bay Area.

Send us your floor plan and your target date and we will build the schedule backwards from it.


Written by the ShipShape Moving team, based on commercial moving experience across Oakland, Berkeley, San Francisco, and the greater East Bay. Building rules, permit requirements, and insurance limits vary by city and by landlord, so confirm current requirements with your property manager and your city before move day.